Newsletter 07 Nov 2004 < click on text to go back to news page

 

The estimated time for completion was October this year, but as we learn all the time, we are always too optimistic about the time plan. The new estimate will be, sailable in January 2005, and final cast off around April 2005.

 

All bulkheads are ready and most of the other frame work, such as cupboards, shelves and sofas are ready and in place. Béa and I are doing the insulation work now. After this the electrical cables have to be drawn, the water and waste system has to be installed, this is not too difficult as cable tubes are prepared in place and water pipes have to be visible (for safety) inside cupboards, below sofas, etc. The electic system will be covered with panels inside and outside of cupboards, ceiling, etc.

 

One of our “headaches” was the construction of a sofa and a cupboard covering the engine box. We have radically changed all special designs by adopting the idea to construct a platform over the whole area. This platform extends in to the L-shaped sofa, which has to be elevated up as well. However, this will give us deeper space inside the sofa for storage. One drawback will be that there will be no 2 metres 5 centimetres headroom around the sofa, but 1 metre and 75 centimetres. The lesser hight to the ceiling will have no inpact on us, as we are shorter than that, both of us. If we have taller guests, they will have to duck just as they have into a sofa on a pilot salon equipped boat.

 

This construction of the area around the sofa will also be easier to make, create more storage space and be less expensive to make. The labour cost in this rebuilding has escalated to sums not planned in the budget, so we have to do most of the easy work ourselves now over the winter. We are simply over the planned budget already and are using the reserves. There are still materiel to be bought and it is mostly vital equipment, this has priority over the labour costs. Béa and  I are looking forward to a busy winter with double working shifts. The good thing we did was to go through every work hour, every little screw and bolt in time before the budget was reaching the limit. At least we have eliminated the surprise part of it. Simply, when the limit is reached, the boat has to be able to sail safely. If some joinery, lists or whatever work is still to do, we will do that later. We think and have been told by so many in the cruising community, go as soon as you can, and this we will do.

 

Last week Sea Otter moved out of the enclosed work-shop and is now parked outside. The mast was stepped at the same time to fit equipment and cables. In January we will take the mast off temporarily, to fit new mainsail sliding system that can take the pressure from the full batten mainsail.

 

New photos will shortly be uploaded to the website.

 

Stay in touch and look after your boats,

 

Until next update, all the best,

 

Chris and Béa.